McMaster Selects a New Learning Management System
Introduction
The Learning Technologies Resource Centre (LTRC) has completed an extensive multi-year project to find the best
possible replacement for WebCT Campus Edition 4.1 (currently in use). The product selected is Blackboard
Learning System Vista Enterprise with Community and Content.
(more ...)
The LTRC along with the LMS Selection Committee and Senior Administration chose the Blackboard Learning System
after extensive analysis of twelve potential products and the teaching and learning needs of the community.
The Daily News announcement is
available on McMaster's Daily News site.
Project Updates
31-Mar-09
- LTRC announces the launch of spring/summer course pilot and the beta-tester program on ELM.
- Please see the launch information page for more detail description of the pilot programs
18-Mar-09
05-Dec-08
- LMS Update report (
) to the committee and community during the Learning Technology Symposium December 3 - 4, 2008
- ELM: E-Learn at Mac is the chosen name for the new Learning System
- The infrastructure staff spent two and a half days along with hardware and Blackboard consultants to install one component of ELM. This major learning component is now installed and the various nodes (machines) and are successfully talking to each other. The rest of the month will be spent installing the other components of ELM, configuring the base installation, as well as intensive testing of the hardware and base installation. Configuration of the application will commence in the new year.
04-Nov-08
The latest project update can be found at the LMS implementation document area.
06-Oct-08
- Success in obtaining the LMS environment name. ELM: eLearning @ McMaster now has its own registered web domain name.
- Clustered install services of the Vista application has been scheduled for December 1st.
- Production Mentoring services (from Blackboard) will commence December 15th.
- The staff have been piloting a new ticketed support system with WebCT. Preliminary result: increased work flow efficiency. This ticketed support system will be used for ELM.
- Training materials development is back in full swing.
15-Sep-08
Hardware
- The majority of the new LMS hardware is racked and assembled. We are still waiting for the arrival
of specialized custom power cables among accessories for the power installation/integration of the new
LMS hardware to the JHE data centre facilities. New ETA is October 6th.
- Moving Forward:
- Cable and accessory installation
- Hardware burn testing (to make sure all the hardware is working properly)
- Operating system and database installation
- Clustered install services of the Vista application: this is tentatively scheduled for November 24th pending availability of Blackboard and a hardware vendor
- Production Mentoring services (from Blackboard) will commence one week after the clustered
install services
- Competing priorities and potential setbacks:
- Scheduling for Bb services
may get pushed further in time depending on availability of consultants. Other work
tasks (e.g. application configuration, data integration, etc. will also be pushed further in time)
- Primary LearnLink online storage needs to be moved to new storage array asap. This will
take place prior to the clustered install services
Other tasks
- The new data streams from UTS/Registrar are in production! The major tasks ahead are
- Develop strategies for data integration (people, courses, enrolments)
- Testing API calls, gathering requirements for XML inputs into the new LMS and programming
- The staff have successfully tested course migrations. As a test, the majority of January 2008 courses were converted from WebCT 4.1 to the Blackboard Vista 8 format. It is likely that on launch of the new system, faculty will receive a sandbox environment containing a blank course as well as converted courses.
- Training material development has begun, but is on hold temporarily as staff support start of term activities for WebCT and LearnLink
05-Sep-08
- The majority of the hardware is racked and assembled. We are still waiting for the
arrival of specialized power cables among other accessories.
- Although development of training materials has begun, it is on hold as staff deal with
the heavy beginning of term support for WebCT and LearnLink.
- The data schema for the new files from UTS/Registrar are now finalized and being moved to production.
- Vista, Community and Content have been installed on the Virtual environment. Preliminary
configurations have begun.
- Discussions have taken place with the University Libraries, HSC Library, Continuing
Education and Student Affairs regarding their needs within the new LMS
Related project documents can be found by visiting the LMS Transition Committee page
I'd like to know more
As we progress through the implementation process, the content at this website will expand.
Last updated:
05-Dec-08
|