LMS Implementation Update

Activities

The following list of activities is not complete, but provides an overview of the tasks that LTRC has to complete in order to get the new LMS up and running. This page will be updated as we proceed through the implementation process. NOTE: this list contains the major "going forward" items only. Everything in the LMS evaluation and selection process that has been accomplished to get us to this point is not shown.

Tecnical Implementation
People/Course Information Integration
Gather Requirements for Server Configuration and Migration
Migration/Training Planning and Strategies
Business Workflow and Policy Development


completed Completed in progressIn Progress not started Not started

Technical Implementation

While WebCT was developed in the early 1990's, the newer version of products from Blackboard were developed less than 5 years ago. Thus, the technical implementation of the new LMS is much more complicated than for the current version of WebCT. To get an idea of the complexity the hardware requirements, view the hardware set up diagram for the current version of WebCT (WebCT hardware pdf) and compare it to the proposed Blackboard implementation (new LMS hardware pdf)

completed Issue RFP for hardware infrastructure (network load balancers, network switches, blade servers, blade storage)
completed Award bid and purchase hardware
completed Secure all software components (BBLS, Operating Systems, Databases)
completed Technical implementation planning with Blackboard (consultation session)
completed Assess suitable location for new infrastructure
completed Site visit to University of Ottawa to see their technical implementation of Blackboard and to discuss implementation best practices (scheduled June 6th)
completed Virtualized environment set up
completed Install, rack and cable hardware
in progress Hardware testing
in progress O/S, Database installation and testing
in progress Clustered installation of applications; clustered environment testing
not started Configure applications
not started Integrate data management
  More to come ...



completed Completed in progressIn Progress not started Not started

People/Course Information Integration
completed Project registration with UTS to obtain new data streams (for people and course information integration)
completed Design schema for data streams
completed Receive data schema for testing
in progress Test design and API (application programming interface) with new LMS to see if people (faculty, staff, student) and course information can be efficiently and effectively integrated
not started Receive live data and integrate
not started Test



completed Completed in progressIn Progress not started Not started

Gather Requirements for Server Configuration and Migration
in progress

There are many identified stakeholders. The LTRC needs to confer and work with all of them to ensure that the configuration of the Learning Management System best meets everyone's needs. Furthermore, now that we know how the new system will function, we can begin to nail down the specifics on integration with various systems such as CAPA (used by Physics), Elluminate, Libraries, etc. A PDF file containing the stakeholders in the project is available for download (stakeholders.pdf )



completed Completed in progressIn Progress not started Not started

Migration/Training Planning and Strategies
completed

Schedule meetings with Associate Deans to address concerns, establish communications, and to identify faculty champions and potential LMS liaisons

completed Communications with Department Chairs and Program Directors to address concerns, establish communications, and to identify faculty champions and potential LMS liaisons
completed Open discussions with faculty and support staff to understand training and migration preferences and concerns
completed Analysis of current tool usage within WebCT
completed Research migration/training strategies at other institutions.
completed Site visit to University of Ottawa planned for June 6th
in progress LMS staff training (Blackboard Product Specialist Training)
completed Administrative training for LMS staff in the LTRC
in progress Establish LMS Liaison network: offer early training, support and communications
completed Test course migration, imports, exports
in progress Develop training materials (face-to-face, online, helpsheets, faq's)
in progress Finalize migration/training plan, communicate, and deploy




completed Completed in progressIn Progress not started Not started

Business Workflow and Policy Development
in progress

Work flow modelling for course creation and people information integration

completed Establish ticketed support system and service level agreements
in progress Course management and access policies development including: copyright, intellectual property, code of conduct, misuse
not started Work with the Office of Academic Integrity to establish policy and procedures for reporting and investigations of misconduct


Last updated: 05-Dec-08
   